How to Read a Contractor Quotation

Two quotes for the same house, Rs 3 lakh apart. Usually neither is cheating. They are quoting different things.

You get three quotations for the same house. One says Rs 1,750 per sq ft, one says Rs 1,900, one says Rs 2,150. The obvious move is to take the cheapest.

The obvious move is usually wrong, because the three of them are not quoting the same thing.

The first question: per sq ft of what?

This single definition moves a quote by 8% to 10%, which on a 1200 sq ft house is nearly two lakh rupees.

TermWhat it means
Carpet areaFloor you can actually walk on. Smallest number.
Built-up areaCarpet plus wall thickness. What most honest quotes use.
Super built-upBuilt-up plus shared areas. Largest number.

A contractor quoting Rs 1,900 on built-up area may well be cheaper than one quoting Rs 1,750 on super built-up. Get every quote onto the same basis before you compare anything.

The follow-up questions

  • Are balconies counted fully, at half, or not at all?
  • Is the staircase included in the area?
  • Is the parking or portico counted?
  • Is the overhead tank slab counted?

Ask all four. If a contractor gets vague here, that vagueness is the quote.

The second question: which materials, by name

"Standard quality" means whatever is cheapest that week. Get brands and grades written into the agreement:

ItemWhat to specify
CementBrand and grade โ€” OPC 43 or OPC 53, or PPC
SteelBrand and grade โ€” Fe500 or Fe550D
BricksType and size, or AAC block brand
TilesRate per sq ft you are being allowed
SanitaryBrand, and the rate allowance
WiringBrand and whether it is ISI marked
DoorsWood type for frames, and shutter type
Why this matters more on a turnkey contract. Once the rate is fixed, every rupee the contractor saves on material is his profit. That is not dishonesty, it is how the contract works. Your protection is the specification, not the price.

The third question: what is excluded?

Do not ask what is included. Ask what is excluded. You will get a much shorter and much more honest answer.

Almost always excluded:

  • Compound wall and gate
  • Borewell, sump, overhead tank
  • Plan sanction and approval fees
  • Site levelling and soil filling
  • Electricity and water connection charges
  • Modular kitchen, wardrobes, furniture

The fourth question: what happens if it takes longer?

A per sq ft contract with no completion date is an open invitation to a slow site. Put a target date in writing. You do not need a heavy penalty clause โ€” just the date being written down changes behaviour.

Payment stages

Never pay a large advance. A normal, safe schedule:

Advance 10% Foundation 15% Plinth 15% Each slab 15% Brickwork 15% Plaster 10% Finishing 15% Handover 5%

Hold that last 5% until every small pending item is genuinely done. It is the only leverage you have at the end, and the end is exactly when things stop moving.

A quick way to sanity-check any quote

Ask for the material list. A contractor who has actually estimated the job can give you one. For 1200 sq ft it should be near:

Cement 480 bags Steel 4,800 kg Sand 2,160 cft Bricks 9,600 nos

If his cement figure is 350 bags, ask why. Maybe he is planning a different structure and has a good answer. Maybe he has not estimated at all and quoted a number that felt right. Either way you have learned something.

The honest summary

The cheapest quote on paper is very often the most expensive by handover, because the gap gets recovered through thinner specification and extras billed later.

Working through a real comparison

Three quotes for the same 1,200 sq ft house:

Quote AQuote BQuote C
Headline rateRs 1,750Rs 1,900Rs 2,150
Area basisSuper built-upBuilt-upBuilt-up
BalconiesCounted fullCounted halfCounted half
Cement gradeNot statedOPC 43OPC 53
SteelNot statedFe500Fe550D
Flooring allowanceNot statedRs 70/sqftRs 95/sqft
Completion dateNone14 months12 months

Quote A looks cheapest and is the least comparable. It quotes on the largest area basis, counts balconies fully, names no material grades and commits to no date. Every one of those is a place where cost comes back later.

Once you convert all three to built-up area with balconies at half, the gap between A and B narrows to almost nothing โ€” and B tells you what you are actually getting.

The questions that expose a thin quote

Ask these five, in this order. The answers matter less than the willingness to answer.

  1. "Is this rate on built-up or super built-up area?" A contractor who has to think about it has not estimated carefully.
  2. "Can you write the cement and steel brands into the agreement?" Reluctance here tells you where the margin is planned.
  3. "What is the flooring and sanitary allowance per sq ft?" Vague answers mean you will be shown the cheapest option and asked to pay extra for anything else.
  4. "What is excluded?" A short list means he has not thought about it. A long, specific list means he has.
  5. "What is your target completion date, and what happens if it slips?" You do not need a penalty. You need the date written down.

Rate allowances: the technique worth using

Most finishing disputes come from arguing about brands. Rate allowances remove the argument entirely.

Instead of "good quality vitrified tiles", write "flooring allowance Rs 90 per sq ft". Now you can pick any tile you like. If it costs Rs 90, nothing changes. If it costs Rs 130, you pay the Rs 40 difference and everyone knows exactly why.

ItemTypical allowance, standard finish
Floor tilesRs 70 โ€“ 110 per sq ft
Wall tiles, bathroomRs 50 โ€“ 80 per sq ft
Sanitary and CP fittingsRs 35,000 โ€“ 60,000 per bathroom
Main doorRs 25,000 โ€“ 45,000
Internal doorsRs 8,000 โ€“ 14,000 each
Kitchen platform and sinkRs 40,000 โ€“ 70,000

Reading the payment schedule

A schedule tied to completed stages is safe. A schedule tied to dates is not, because you can end up having paid 60% for 35% of the work.

Advance 10% Foundation 15% Plinth 15% Each slab 15% Brickwork 15% Plaster 10% Finishing 15% Handover 5%

Two rules that matter more than the exact percentages:

  • Never pay ahead of a stage. Payment follows completed work, not promised work.
  • Hold the final 5% properly. It is your only leverage on the pending list, and the end is exactly when small items stop getting finished.

Clauses worth adding

ClauseWhy
Defect liability, 12 monthsCovers leaks and cracks that show up in the first monsoon
Who bears material wastagePrevents the argument at the end of a labour rate contract
Structural drawing to be followedStops on-site improvisation on steel
Site to be handed over cleanDebris removal is otherwise billed as extra
Written approval for any extraNo verbal extras appearing on the final bill

Questions people ask

Is the cheapest quote always bad?

No. Sometimes a contractor is between projects and wants the work, or lives nearby and saves on travel. The point is not to reject cheap quotes โ€” it is to make sure it is cheap for a reason you can identify.

Should I show one contractor another's quote?

Better to share the specification and ask everyone to quote against it. Sharing prices invites matching on number while quietly cutting elsewhere.

How many quotes should I get?

Three is enough. More than that and you spend weeks comparing without learning anything new.

What if he refuses to write brands in the agreement?

That is your answer. A contractor confident in his costing has no reason to resist naming what he already intends to buy.

Spend your effort on the specification, not on beating down the rate by fifty rupees. A well-specified contract at Rs 1,950 beats a vague one at Rs 1,750 almost every time.

Run your own numbers. The House Construction Cost Calculator does the working shown above for your plot, city and specification.